Featured Posts

Night work and new signs

The Dundas Place construction zone might have looked less busy than usual during the day, but don’t be fooled! Crews have been working over night to prepare for the new watermain installation. Let me back track a little to explain why they switched their working hours.

In order for crews to remove and replace the existing watermain, they have to install temporary water pipes to continue to serve the businesses and residents with water. Before we could make the official switch to the temporary watermain, we had to test the pipes to make sure the water was clean and safe to drink.

 

On Monday, tests confirmed that these temporary pipes were good to go and ready to serve Dundas Street! This meant we could begin preparations for the new, more reliable watermain. Part of that prep work involves connecting the temporary pipes to the existing ones. To minimize disruption, watermain connection work is done in the evenings to help minimize water shut-off periods. You can expect regular construction activity to continue between the hours of 9 p.m. to 7 a.m. into next week. 

While there's no construction going on over the long weekend, you'll notice the new temporary lighting that illuminates the street allowing you to navigate the construction zone with ease!

What you might also notice is some new signs on the construction fencing. This is just a taste of a series of signs that will go up over the next month. You'll start to see some familiar faces and some new phrases which we hope inspire you to walk a little farther and experience what Dundas Place has to offer. 

 

 

Below is a summary of work completed the week of May 14 to 18 and next steps for the week ahead. 

 

Work completed this week
- Temp watermain connection at Ridout St

- Bell mainline work completed between Ridout St to Talbot St

- Temp Hydro line work completed between Talbot St to Richmond St

- Temp hydro pole installation completed, temp street light energized

Work anticipated next week
- Fiber optic installation at Ridout St intersection

- Commissioning temp watermain

- Temp water service switch over at properties
- Hydro mainline work between Talbot St to Richmond St

Share on Facebook
Share on Twitter
Please reload

A year in review & holidays wishes from the crew

December 20, 2019

1/1
Please reload

Recent Posts

October 26, 2019

Please reload

Archive
Please reload

Search By Tags
Please reload

#dundasplace

  • Grey Twitter Icon
  • Grey Facebook Icon
  • Grey Instagram Icon

Dundas Place is the first transformational project in Our Move Forward, London's Downtown Plan and a 2019 core construction project. To learn more, visit: london.ca/coreconstruction

City of London Logo

© 2019 City of London.