The crew was able to get started right away on the re-pour of concrete on the roadway east of Clarence Street. Early in the week, you may have noticed the crew working later into the evening in order to stay on track since we knew the rain was coming. 

Crews not only made progress with concrete on the roadway, but also in the sidewalk area. The majority of the concrete on the north side of the block between Wellington Street and Clarence Street is now complete. Meanwhile, the crew is trying their best to get all of the duct work completed over at the intersection of Clarence and Dundas so it can be covered in concrete sooner than later.

Despite the steady rain on Wednesday and Thursday, we were still able to complete some important milestones like getting tree planting done across from Budweiser Gardens and east of Richmond Street.

We were thrilled to hear that the Downtown Candy Crawl was a hit, with more than one hundred trick-or-treaters making their way through the construction zone, down all four blocks of Dundas Place. We hope everyone enjoyed the treats, and the stops along the way! 

 

 

Share on Facebook
Share on Twitter
Please reload

A year in review & holidays wishes from the crew

December 20, 2019

1/1
Please reload

Recent Posts

October 26, 2019

Please reload

Archive
Please reload

Search By Tags
Please reload

#dundasplace

  • Grey Twitter Icon
  • Grey Facebook Icon
  • Grey Instagram Icon

Dundas Place is the first transformational project in Our Move Forward, London's Downtown Plan and a 2019 core construction project. To learn more, visit: london.ca/coreconstruction

City of London Logo

© 2019 City of London.